In partnership with

Welcome back to Beyond Deadlines newsletter—a free perk for people looking to improve in Planning and Scheduling. Each week, we provide tactics, prompts, jobs and food for thought. We want you to succeed today, tomorrow and throughout the rest of your career.

Of all the factors that have been studied, the strongest known force in daily motivation is a sense of progress.

Hidden Potential by Adam Grant

The Daily Newsletter for Intellectually Curious Readers

Join over 4 million Americans who start their day with 1440 – your daily digest for unbiased, fact-centric news. From politics to sports, we cover it all by analyzing over 100 sources. Our concise, 5-minute read lands in your inbox each morning at no cost. Experience news without the noise; let 1440 help you make up your own mind. Sign up now and invite your friends and family to be part of the informed.

8 Tactics to Nail Your Construction Schedule Baseline Review

A weak baseline review sets you up for rework, chaos, and missed milestones. A great one? It locks in logic, earns field buy-in, and clears the runway for execution.

If you're a scheduler or PM who actually wants the job to flow, this is your moment. Here’s how to lead a baseline review that gets taken seriously on site:

1. Start with targeted pre-work.
Send a one-pager with focused prompts on phasing, access, and float. Add a 2-minute quiz. Incentivize it. When people show up prepared, you don’t waste the first hour repeating basics, you go straight to value.

2. Bring the build to life.
Show the job on paper, on screen, in 4D. Use printouts, layout boards, models, logic paths. People catch missed scopes and clashes when they see them, not when they’re talked at.

3. Break the day into buildable blocks.
Don’t cram everything into one drawn-out session. Split the review into focused phases structure, MEP, turnover. Use breakout groups to solve specific issues, then reconvene. Add breaks to keep energy up.

4. Get the right boots in the room.
Schedulers alone won’t catch it all. Involve superintendents, foremen, and commissioning leads. They see what software doesn’t, handoffs, sequencing gaps, space conflicts. Make their voice part of the review.

5. Create a live challenge.
Run a mini-comp: Who finds the biggest logic flaw? Who saves the most time? Even a $20 prize gets people leaning in. Gamify participation to get sharper thinking in the room.

6. End with alignment, not homework.
You’re not aiming for “we’ll follow up”, you’re aiming for a signed-off baseline. Lock it in. When the review ends, everyone should know what’s happening, when, and why.

7. Follow up fast or lose them.
If you wait three days to send notes, you've lost momentum. Follow up that same afternoon with 3 things: what changed, what got locked, and a quick thank you. Keep it clear, visual, and short. Engagement dies in long emails, don’t let the energy go cold.

8. Celebrate like the baseline matters because it does.
You just got buy-in from field, trades, and execs. You locked the logic that’s going to drive months of work. That’s not a “donut in the trailer” moment, that’s a team milestone. Host a crew dinner. Invite families. Make it personal. Show people their input built something real. When you celebrate like the schedule matters, they’ll protect it like it does.

Most baseline reviews are passive. Yours shouldn’t be.

This is your shot to shape the plan before the plan shapes you.

Creating a baseline review workshop agenda

Copy and paste this prompt into ChatGPT, Gemini or Claude.

Act like a veteran construction-scheduling consultant and workshop facilitator with 15+ years of experience aligning large infrastructure projects.
Your task is to guide the creation of a Schedule Baseline Review (SBR) full-day workshop whose outcome is a fully agreed and signed-off baseline schedule. You will first collect concise inputs from the scheduler, then automatically generate:

  1. Pre-work assignments for all participants.

  2. A detailed, time-boxed agenda (default 08:00 – 17:00) broken down by actual project phases / trade scopes rather than generic scheduling topics.

  3. Post-work follow-up actions to lock the baseline into the scheduling tool and circulate decisions.

🛠️ Step 1 — Gather Key Inputs for Baseline Review Agenda

Schedulers: Fill in clear, brief responses. Only use “N/A” if something truly doesn’t apply. Your answers directly shape the agenda and focus of the baseline review.

  1. 🔧 Project Basics

    • Project Name & ID:

    • Delivery Method (DBB, Design-Build, CM/GC, etc.):

    • Key Milestone Dates (e.g., NTP, Mobilization, Substantial Completion):

    • Scheduling Tool & Version (P6, ASTA, MS Project, etc.):

    • Owner Scheduling Specification / Requirements (attach or paste key clauses):

  2. 📅 Workshop Logistics

    • Target Workshop Date:

    • Location or Virtual Platform (e.g., trailer, Teams, Zoom):

    • Planned Start and End Time (default: 08:00 – 17:00):

  3. 👷 Who’s in the Room?

    • Core Team Members (Names & Roles):

    • Represented Companies (GC, Owner, CM, Subcontractors):

    • Trade Types / Scopes Needed (MEP, structure, utilities, envelope, etc.):

    • Decision-Maker for Final Sign-Off (Name & Role):

  4. 📈 Schedule Snapshot

    • Current Schedule Revision/ID:

    • Total Activity Count & WBS Depth:

    • Design Completion % (if still in design):

    • Known Risks or Constraints (access, long-leads, sequencing, site logistics):

  5. 💰 Resource & Cost Integration

    • Is the Schedule Resource-Loaded? (Yes/No):

    • Is the Schedule Cost-Loaded or Budget-Linked? (Yes/No):

  6. 🎯 Focus Areas for Review

    • Interfaces with Other Projects, Phases, or Utility Work:

    • Regulatory or Permit-Driven Constraints:

    • Critical Path or Near-Critical Paths to Watch:

    • Primary Phases / Trade Scopes to Review (list in preferred order, e.g., Site Prep, Foundations, Structure, Envelope, MEP Rough-In, Interior Finishes, Commissioning):

    • Recommended Review Sequence (if specified by owner spec or project logic):

🔍 Step 2 — Pre-work Package

For each participant group, auto-generate clear instructions based on their role, including:

  • Reading assignments (latest schedule, scope documents, risk register).

  • Data to bring (updated quantities, resource calendars, crew rates).

  • One slide summarizing their top three concerns for their specific phase / trade scope.

🗓️ Step 3 — Draft the Full-Day Agenda by Project Phase / Trade Scope

Use the phase / scope list provided in Step 1 ▸ Focus Areas to build the agenda. Allocate time so the blocks sum to the available workshop hours, include breaks, and sequence the discussion to follow the way the project will actually be built. A sample structure is shown below (adjust timings, titles, and leads automatically to match user inputs):

Time

Agenda Block

Purpose

Lead (by scope)

Key Output

08:00

Project Flow Overview & 4D Walkthrough

Visualize end-to-end build sequence; confirm review order

Scheduler

Agreed review roadmap

08:30

Phase 1 – Site Prep / Enabling Works

Validate activities, logic, resources

Civil Lead

Updated Site Prep segment

09:15

Phase 2 – Foundations & Structure

Confirm sequencing, crane logistics, concrete durations

Structural Lead

Approved foundational logic

10:15

Break

10:30

Phase 3 – Envelope / Superstructure

Align steel/skin installation vs. weather windows

Envelope Lead

Locked-in envelope plan

11:15

Phase 4 – MEP Rough-In (Mechanical, Electrical, Plumbing)

Review prefab opportunities, access, clashes

MEP Leads

Coordinated MEP rough-in

12:00

Lunch

13:00

Phase 5 – Interior Build-Out & Finishes

Tie finish sequencing to material lead times

Interiors Lead

Approved interior schedule

13:45

Phase 6 – Commissioning, Start-Up & Testing

Validate durations vs. specs, integrate submittal flow

Commissioning Agent

Commissioning timeline

14:30

Break

14:45

Interfaces, External Works & Utility Tie-ins

Coordinate with adjacent projects / authorities

Interface Manager

Agreed interface dates

15:30

Risk, Weather & Contingency Review

Embed mitigations, float, weather allowances

Risk Manager

Updated risk register links

16:00

Baseline Sign-Off & Next Steps

Secure approvals, assign action items

Exec Sponsor

Signed baseline form

16:30

Buffer / Overrun Time

Resolve outstanding items

Scheduler

Final tweaks

17:00

Adjourn

Baseline locked

Automatically scale or split blocks if additional phases (e.g., Utilities, Landscaping, Demobilization) are supplied.
Attach facilitator notes prompting live schedule edits, decision logging, and parking-lot tracking.

📌 Step 4 — Post-work Actions

Automatically list tasks such as:

  1. Enter agreed changes in the scheduling tool and rerun CPM.

  2. Recirculate the final PDF and native file to all stakeholders within 24 h.

  3. Update the risk register and cost forecast.

  4. File the signed baseline approval in project document control.

  5. Schedule a 30-day baseline health-check meeting.

📤 Output Format

After collecting answers to Step 1, display:

  1. Pre-work package (bulleted by role).

  2. Workshop agenda in the phase-based table layout above, fully tailored to the inputs.

  3. Post-work action list.

  • Company - Motorola

  • Location - Remote

  • Company - GE Vernova

  • Location - Remote

  • Company - Oralce

  • Location - Remote

We have no connection to these jobs or companies. Our goal is simply to help you land the job of your dreams.

Greg and I launched our book on The Physics of Project Acceleration. A how-to guide for making your projects go faster. 
From simple builds, to billion-dollar data centers. Preorder your copy here.

Thank you for reading.

Check out Micah, Greg and Beyond Deadlines on LinkedIn.

Sign up for our LinkedIn newsletter.

Subscribe to our YouTube Channel.

Listen to the podcast on Spotify or Apple Podcasts. Visit our website.

See you next week,