Welcome back to Beyond Deadlines newsletterā€”a free perk for people looking to improve in Planning and Scheduling. Each week, we provide tactics, prompts, jobs and food for thought. We want you to succeed today, tomorrow and throughout the rest of your career.

I feel like your problem is that youā€™re trying to judge all things in the abstract before you do them. Thatā€™s your tragic mistake.

So Good They Canā€™t Ignore You by Cal Newport

Winter Style Starts with Nike Air Max.

Discover the Nike Air Max collection designed just for men. With standout styles like the Air Max Plus, AM1, DN, and Pulse, these sneakers combine innovative technology and eye-catching designs. Each model offers cushioned support and versatility, making them perfect for any occasion.

5 Primavera P6 Layout Tips Youā€™ll Wish You Knew Sooner

Most senior schedulers know the basics of Primavera P6 layouts. But mastering the lesser-known tactics? Thatā€™s where the real productivity boost happens.

Here are 5 quick wins to make your layouts smarter, faster, and more insightful:

1ļøāƒ£ Use Custom Filters for Smarter Views
Stop scanning endless schedules. Custom filters show you only what matters:

  • Critical Path: Filter Total Float = 0 to see only the critical path.

  • Risky Activities: Spot negative float or high total float activities.

  • Resource Overload: Pinpoint tasks where Remaining Units > Available Units.

  • Logic Gaps: Identify tasks with no predecessor or successor (aka, schedule risks).

Pro Tip: Use logic-driven filters like "Where Duration > 20 days" to spot long-duration tasks that might need attention.

2ļøāƒ£ Master Custom Columns for Sharper Insights
Columns arenā€™t just Start and Finish. Hereā€™s what the pros track:

  • Float Path: See which tasks are driving the project completion date.

  • Relationship Lag: Spot lag that could be dragging your schedule.

  • Constraint Date & Type: Identify "locked" tasks that could be a risk.

  • Actual This Period: See current-period progress for sharper reports.

Pro Tip: Combine custom columns with grouping to visualize key data by % Complete, Total Float, or Responsibility.

3ļøāƒ£ Customize Grouping for Clarity
Grouping isnā€™t just for WBS. Hereā€™s how to turn chaos into clarity:

  • By Total Float Bands: Group tasks into 0-5, 5-10, and 10+ day float ranges.

  • By Resource Name: See where your team is overloaded.

  • By Responsibility: Spot subcontractor accountability at a glance.

Pro Tip: Color-code Gantt bars (e.g., red for critical, gray for non-critical) for instant visual clarity.

4ļøāƒ£ Customize Bars to Spotlight Key Data
Custom Gantt bars aren't decoration ā€” they're clarity tools.

  • Progress Indicators: Color-fill to visualize progress (e.g., green-to-red gradients).

  • Custom Milestone Bars: Differentiate Contractual, Payment, and Internal milestones.

  • Relationship Lag: Show lead/lag directly on the Gantt for visual logic clarity.

Pro Tip: For presentations, keep it simple: Critical Path, Milestones, and Summaries only.

5ļøāƒ£ Build a QA/QC Layout to Catch Mistakes
Donā€™t wait for audits ā€” find your own mistakes first.

  • Key Columns: Add Total Float, Open Ends, Constraints, Leads, and "Actual Start Without Remaining Duration."

  • Smart Filters: Spot issues with ā€œOpen Endsā€ (tasks with no predecessors/successors) and ā€œLeadsā€ (negative lag).

  • Group by Issue Type: Tackle issues by priority (e.g., Open Ends, Lead Use, Constraint Issues).

Pro Tip: Save your QA/QC layout and use it before every schedule update. Catch the mistakes before your client does.

Write a Schedule Narrative

Copy and paste this prompt into ChatGPT, Gemini or Claude.

Act as a world-leading Construction Scheduler with 20 years of experience and unparalleled expertise in reviewing Primavera P6 schedule .pdfs. Your task is to create a comprehensive and engaging schedule narrative that provides clear insights for project stakeholders.

The context is that you are delivering a monthly project update, and your narrative must address key aspects of the schedule. Draw from best practices in schedule analysis, including an executive summary highlighting high-level progress, a detailed critical path analysis, an overview of this monthā€™s progress, and an assessment of key potential risks and mitigation strategies.

The format should be well-structured with clear headings and concise, professional language. The tone should be authoritative, precise, and proactive, ensuring stakeholders feel informed and confident in the projectā€™s direction. Before you begin, ask me 3 questions to help improve your answer.

  • Company - Microsoft

  • Location - Oregon, United States

  • Company - Blue Origin

  • Location - Seattle, WA, United States

Planner/Scheduler (Maintenance)

  • Company - Amazon

  • Location - Mount Juliet, TN, United States

We have no connection to these jobs or companies. Our goal is simply to help you land the job of your dreams.

Sponsored
MGMT PlaybookPractical management insights straight to your inbox every Wednesday.

This weekā€™s episode we dive into collaboration. Watch or Listen on Spotify, Apple Podcasts or Youtube.

Stay up-to-date with AI

The Rundown is the most trusted AI newsletter in the world, with 800,000+ readers and exclusive interviews with AI leaders like Mark Zuckerberg.

Their expert research team spends all day learning whatā€™s new in AI and talking with industry experts, then distills the most important developments into one free email every morning.

Plus, complete the quiz after signing up and theyā€™ll recommend the best AI tools, guides, and courses ā€“ tailored to your needs.

Thank you for reading.

Check out Micah, Greg and Beyond Deadlines on LinkedIn.

Sign up for our LinkedIn newsletter.

Subscribe to our YouTube Channel.

Listen to the podcast on Spotify or Apple Podcasts. Visit our website.

See you next week,